2009/07/10

  • Plastering of front Sky wall continued
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • Continued repairing of Louvers of windows
  • Started laying of roof tiles on small pavilions.
  • Work delayed due to rain

2009/07/09

  • Plastering of front Sky wall continued
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • Continued repairing of Louvers of windows
  • Roof tile transported to the site

2009/07/08

  • The Form Work of Pillars of the Makara Thorana completed
  • Casting of Walakulu Bemma on the South Boundary wall completed. Plastering of front Sky wall continued
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • Continued repairing of Louvers of windows
  • Work delayed due to rain

2009/07/07

  • The Form Work of Pillars of the Makara Thorana continued
  • Casting of Walakulu Bemma on the South Boundary wall continued. Plastering of front Sky wall continued
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • Continued repairing of Louvers of windows
  • Work delayed due to rain

2009/07/06

  • The Monks were invited for the Wassana Kala in the morning and the delegation left Lumbini.
  • The Form Work of Pillars of the Makara Thorana continued
  • Casting of Walakulu Bemma on the South Boundary wall continued
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • Continued repairing of Louvers of windows

2009/07/05

  • The new website for the Sri Lanka Maha Vihara (www.lumbinisudeesa.org) was launched by Mr. Thosapala Hewage H.E. The Sri Lankan Ambassador for Nepal with the chanting of Seth Pirith
  • The site was inspected by Mr. Thosapala Hewage H.E. The Sri Lankan Ambassador for Nepal with the Comiittee.
  • A meeting was held in the evening to discuss about the progress and the future plans
  • The Form Work of Pillars of the Makara Thorana continued
  • Casting of Walakulu Bemma on the South Boundary wall continued
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • Continued repairing of Louvers of windows

2009/06/30

  • The Form Work of Pillars of the Makara Thorana continued
  • Casting of Walakulu Bemma on the South Boundary wall continued
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • Continued repairing of Louvers of windows

2009/06/29

  • The Pillars of the Makara Thorana concreted
  • Casting of Walakulu Bemma on the South Boundary wall continued
  • Continued repairing of Louvers of windows
  • Continued cutting & polishing of Marble. Final touches of Steps continued

2009/06/28

  • A rainy day. No work done
  • Continued repairing of Louvers of windows

2009/06/27

  • The Form Work of Pillars of the Makara Thorana continued
  • Casting of Walakulu Bemma on the South Boundary wall and Plastering of North Walakulu Bemma continued
  • Replacement of roof tiles started on Resource Center
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • Continued repairing of Louvers of windows