Posted in Progress on Mar 29th, 2009
Till 12 noon the Strike and the curfew lifted. No material can be transported.
Completed the North boundary walls to 18 in x 18 in as shown in figure.
Glaze tiling could not be done because of the unavailability of tile transportation.
Rough tiling on Outer Curved Mote walls 90% completed. Southern Large pavilion 90% completed.
Varnishing underneath [...]
Read Full Post »
Posted in Progress on Mar 28th, 2009
The Strike and the curfew continued for the second day at Bhairahawa & Butwal Areas. No material can be transported.
Completed the North boundary walls to 18 in x 18 in as shown in figure.
Glaze tiling of the hall of the second floor in the Left wing building completed. Balcony 80% done. Work temporary stopped [...]
Read Full Post »
Posted in Progress on Mar 27th, 2009
Completed the North boundary walls to 18 x 18 in. Eastern Side finished up to 60%
Glaze Tiling on cement benches in side of the Right wing building completed.
The hall of the second floor of the Left wing building continued. 90% completed. Balcony 30% done.
Varnishing underneath right wing building 90% completed
Again the Strike started and [...]
Read Full Post »
Posted in Progress on Mar 27th, 2009
Interview was held at Dhangadi Buddhist Temple. 11 boys were Selected. The responsible Lady also in one of the pictures.
Continued the next step of North boundary walls. 50% completed
Laying of Green Marble in the Small pavilion, front of Left wing building completed.
Glaze Tiling on cement benches in side of the Right wing building continued [...]
Read Full Post »
Posted in Progress on Mar 27th, 2009
Proceeded to Dhangadi (10 Hour journey, One way) to select the Boys to be ordained.
Obtained over the phone the following work progress during the day.
Continued the next step of North boundary walls.
White Marble work inside of the Siddhartha pavilion completed.
Laying of Green Marble in the Small pavilion, front of Left wing building continued. [...]
Read Full Post »
Posted in Progress on Mar 24th, 2009
Started the next step of North boundary walls
White Marble work inside of the Siddhartha pavilion continued. 90% completed
Laying of Green Marble in the Small pavilion, front of Left wing building started.
Roof timber varnishing right wing building 1st coat continued. 60% completed.
Another gang of skilled labourers came to site for Tile work
Read Full Post »
Posted in Progress on Mar 24th, 2009
Foundations of the boundary walls North side completed
White Marble work inside of the Siddhartha pavilion continued. 50% completed
Roof timber varnishing right wing building 1st coat started. 40% completed.
Part of Materials such as Rubble, Glaze Tiles and Sand transported to the site
Read Full Post »
Posted in Progress on Mar 22nd, 2009
Continued foundations of the boundary walls North side as shown in figure
White Marble work inside of the Siddhartha pavilion continued.
Sample of glaze tiles for the pond front of Siddhartha pavilion brought.
Laying of rough tile on the curved mote wall, sample of 10 ft. shown and approved.
Contractor brought estimates for electrical work & [...]
Read Full Post »
Posted in Progress on Mar 22nd, 2009
Continued foundations of the boundary walls North side
Glaze tile design and Colour approved for the left wing building
White marble work inside of the Siddhartha pavilion continued
Contractor came to the site and he was advice to speed up the work. Warned him at least to send a translator to the site
Read Full Post »
Posted in Progress on Mar 22nd, 2009
Continued foundations of the boundary walls North side
Varnishing underneath Bodhi Ghara completed
First coat varnishing started out side of walls of the Left wing Building
Thunder showers at mid night lasted for almost one hour
Read Full Post »