Monthly Archive for March, 2009

2009/03/19

Returned to Lumbini from Katmandu
Boundary wall was done as per instructions as shown in the figure.
Varnishing second coat done underneath 08 small pavilions
Started varnishing the left wing, out side brick wall
Material been transported to the site including Rubble

Read Full Post »

2009/03/18

Contractor informed that the materials are being transported

Read Full Post »

2009/03/17

Contractor phoned to start the white marble work in Siddhartha Pavilion and permission granted

Read Full Post »

2009/03/16

Proceeded to Katmandu for the extension of Visa

Read Full Post »

2009/03/15

Strike ended
Contractors came to the site in the afternoon and discussed about the work to be done
Instructions were given to continue the second coat varnishing of timber underneath all pavilions
Foundations to be done were instructed.

Read Full Post »

2009/03/14

Strike continued for the 3rd day. No work done.
Spoke to the Contractor over the phone and requested into transport materials to the site if possible, during the night. He told that there are no hardware stores open and no vehicles are willing to come.

Read Full Post »

2009/03/13

Strike continued for the 2nd day. No materials were transported to the site.
Part of the painting of window sashes with available brown enamel paint continued.
Brick work done underneath the steps for store room.
Practically no work done.

Read Full Post »

2009/03/12

Internal Painting of Left wing Building continued after the Holidays
No work because of the “Holy” Festival
Strike restarted after the “Holy” festival

Read Full Post »

2009/03/11

No work because of the “Holy” Festival

Read Full Post »

2009/03/10

Strike continued for the 10th day.
No work because of the “Holy” Festival

Read Full Post »