Posted in Progress on Apr 30th, 2009
Completed Brick Wall on North Boundary wall for the Walakulu Bemma. Started both Eastern walls.
Started & completed tiling at Dana Shala.
Continued repairing the damaged louvers of the left wing building
Stainless Steel Hand Rail continued.
Continued Colour washing inside of the right wing building
Second coat terracotta paint on right wing roof completed replacing damaged tiles. Small Pavilions [...]
Read Full Post »
Posted in Progress on Apr 30th, 2009
Continued Brick Wall on North Boundary wall for the Walakulu Bemma
Completed laying of tiles inside of the Pound
Continued repairing the damaged louvers of the left wing building
Stainless Steel Hand Rail continued.
Second coat terracotta paint on right wing roof completed replacing damaged tiles. Small Pavilions continued.
Glaze tile work continued in 1st floor in side of the [...]
Read Full Post »
Posted in Progress on Apr 30th, 2009
Continued Brick Wall on North Boundary wall for the Walakulu Bemma
Continued laying of tiles inside of the Pound
Continued repairing the damaged louvers of the left wing building
Stainless Steel Hand Rail continued. 70% done.
Completed concreting on western boundary wall towards the main entrance
Second coat terracotta paint on right wing roof completed replacing damaged tiles. Small Pavilions [...]
Read Full Post »
Posted in Progress on Apr 27th, 2009
Started Brick Wall on North Boundary wall for the Walakulu Bemma
Started laying of tiles inside of the Pound
Continued repairing the damaged louvers of the left wing building
Stainless Steel Hand Rail continued
Started concreting on western boundary wall towards the main entrance
Second coat terracotta paint on right wing roof continued replacing damaged tiles. completed two small pavilions
Glaze [...]
Read Full Post »
Posted in Progress on Apr 27th, 2009
Continued repairing the damaged louvers of the left wing building
Stainless Steel Hand Rail continued
Continued shuttering & reinforcement works on western boundary wall towards the main entrance
Second coat terracotta paint on right wing roof continued replacing damaged tiles. Continued two small pavilions
Glaze tile work continued in 1st floor in side of the left wing building. [...]
Read Full Post »
Posted in Progress on Apr 27th, 2009
Started repairing the damaged louvers of the left wing building
Stainless Steel Hand Rail continued
Started shuttering & reinforcement works on western boundary wall towards the main entrance
Second coat terracotta paint on right wing roof continued replacing damaged tiles. Continued two small pavilions
Putting of damage areas of pillars inside of Siddhartha pavilion completed
Glaze tile work continued [...]
Read Full Post »
Posted in Progress on Apr 25th, 2009
Stainless Steel Hand Rail continued
Continued laying of 6 in. concrete layer on eastern boundary wall
Second coat terracotta paint on right wing roof continued replacing damaged tiles. Started two small pavilions
Putting of damage areas of pillars inside of Siddhartha pavilion continued
Glaze tile work continued in 1st floor in side of the left wing building
Wiring inside of [...]
Read Full Post »
Posted in Progress on Apr 25th, 2009
Stainless Steel Hand Rail continued
Continued laying of 6 in. concrete layer on eastern boundary wall
Second coat terracotta paint on right wing roof continued replacing damaged tiles
Putting of damage areas of pillars inside of Siddhartha pavilion started
Glaze tile work continued in 1st floor in side of the left wing building
Wiring inside of the left wing building [...]
Read Full Post »
Posted in Progress on Apr 25th, 2009
Stainless Steel Hand Rail continued
Started laying of 6 in. concrete layer on eastern boundary wall
The corners of the Western & Southern boundary walls on the concrete beams completed.
Second coat terracotta paint on right wing roof continued replacing damaged tiles
Glaze tile work continued in 1st floor in side of the left wing building
Wiring inside of [...]
Read Full Post »
Posted in Progress on Apr 25th, 2009
Completed laying of White Marble under stair
Rough tile work on Round walkways to the Uda Maluwa & steps completed. Finishing touches to be started later
Stainless Steel Hand Rail continued
The corners of the Western & Southern boundary walls on the concrete beams continued.
Second coat terracotta paint on right wing roof started replacing damaged tiles
Glaze tile [...]
Read Full Post »