Monthly Archive for April, 2009

2009/04/19

Continued laying of White Marble under stair
Rough tile work on Round walkways to the Uda Maluwa & steps continued.
Stainless Steel Hand Rail continued
The corners of the Western & Southern boundary walls on the concrete beams started.
Wiring inside of the left wing building continued
Plumbing in side of the Left Wing Building continued

Read Full Post »

2009/04/18

Continued laying of White Marble under stair
Rough tile work on Round walkways to the Uda Maluwa & steps continued.
Stainless Steel Hand Rail continued
The corner of the Western & Southern boundary walls concrete column & the beams completed.
Wiring inside of the left wing building continued
Plumbing in side of the Left Wing Building continued

Read Full Post »

2009/04/17

Wiring inside of the left wing building continued
Continued laying of White Marble under stair
Rough tile work on Round walkways to the Uda Maluwa & steps continued.
Started the Stainless Steel Hand Rail
The corner of the Western & Southern boundary walls concrete column & the beams continued.
Plumbing in side of the Left Wing Building continued

Read Full Post »

2009/04/16

Wiring inside of the left wing building continued
Continued laying of White Marble under stair
Rough tile work on Round walkways to the Uda Maluwa & steps continued.
Completed laying of Red Marble on the edges of Main Steps
The corner of the Western & Southern boundary walls concrete column & the beams started.
Plumbing in side of the [...]

Read Full Post »

2009/04/15

Wiring inside of the left wing building continued
Continued laying of White Marble under stair
Rough tile work on Round walkways to the Uda Maluwa & steps continued.
Continued laying of Red Marble on the edges of Main Steps
Completed the balance work of the southern boundary wall & continued the western boundary walls up to 18 in x [...]

Read Full Post »

2009/04/14

Wiring inside of the left wing building continued
Continued laying of White Marble under stair
Silicon Painting of bricks out side walls of the right wing building continued.
Rough tile work on Round walkways to the Uda Maluwa & steps continued
Started laying of Red Marble on the edges of Main Steps
Continued the balance work of the southern & [...]

Read Full Post »

2009/04/13

Wiring inside of the left wing building continued
Continued laying of White Marble under stair
Silicon Painting of bricks out side walls of the right wing building continued.
Pedestal in side of the Siddhartha pavilion completed
Rough tile work on Round walkways to the Uda Maluwa & steps continued
Continued the balance work of the southern boundary wall up to [...]

Read Full Post »

2009/04/12

Wiring inside of the left wing building continued
Started laying of White Marble under stair
Silicon Painting of bricks out side walls of the right wing building continued.
Pedestal in side of the Siddhartha pavilion continued
Rough tile work on Round walkways to the Uda Maluwa & steps continued
East boundary wall, (18 in x 18 in) completed. Continued the [...]

Read Full Post »

2009/04/11

Putting & Painting of the Painting walls behind the Siddhartha pavilion completed
Concreting completed under the stairs & Siddhartha Maluwa for laying of White Marble
Pedestal in side of the Siddhartha pavilion continued
Brown enamel painting of windows & doors of the right wing building continued
Silicon Painting of bricks out side walls of the right wing building continued.
Rough [...]

Read Full Post »

2009/04/10

Brown enamel painting of windows & doors of the right wing building continued
Silicon Painting of bricks out side walls of the right wing building continued.
East boundary wall, (18 in x 18 in) continued. 90% completed. Started the balance work of the southern boundary wall
Plumbing in side of the Left Wing Building continued
Putting & Painting of [...]

Read Full Post »