Monthly Archive for May, 2009

2009/05/30

Cutting of the foundation of the Makara Thorana was started at auspicious time (11.45 am) with the chanting of Seth Pirith by Ven. Dr. Rambukwelle Chandrarathana Thero and the Little Monks.
Casting of Walakulu Bemma on the East Boundary wall along with the access road continued with one mold. Continued making of new 04 molds.
Brick work [...]

Read Full Post »

2009/05/29

A Meeting held with Mr. Semage to decide Makara Thorana placing & levels. Main entrance to be filled from both sides with earth to match the levels of Walakulu Bemma & Makara Thorana.
Casting of Walakulu Bemma on the East Boundary wall along with the access road continued with one mold. Continued making of new 04 [...]

Read Full Post »

2009/05/28

Casting of Walakulu Bemma on the East Boundary wall along with the access road continued with one mold. Continued making of new 04 molds.
Brick work of the east boundary wall restarted.
Continued cutting & polishing of Marble.
Continued Mosaic tiling out side round pavement of the Lower Maluwa.
Continued floor tiling & wall tiling in toilets in side [...]

Read Full Post »

2009/05/27

Casting of Walakulu Bemma on the East Boundary wall along with the access road continued. Started making of another 04 Wooden Molds.
Continued cutting & polishing of Marble.
Plastering continued inside of the toilets in Left Wing building
Continued Mosaic tiling out side round pavement of the Lower Maluwa.
Continued floor tiling & wall tiling in toilets in ground [...]

Read Full Post »

2009/05/26

Casting of Walakulu Bemma on the East Boundary wall along with the access road continued
Continued cutting & polishing of Marble.
Continued Mosaic tiling out side round pavement of the Lower Maluwa.
Continued floor tiling & wall tiling in toilets in ground & 1st floors of the Left wing building.
Plastering continued inside of the toilets in Left Wing [...]

Read Full Post »

2009/05/25

Completed fixing fence posts on western boundary wall.
Continued cutting & polishing of Marble.
The Mural on left side wall of the main mural continued
Continued Mosaic tiling out side round pavement of the Lower Maluwa. Continued floor tiling & wall tiling in toilets in ground & 1st floors of the Left wing building.
Plastering continued inside of the [...]

Read Full Post »

2009/05/24

Continued fixing fence posts on western boundary wall.
Continued cutting & polishing of Marble.
The Mural on left side wall of the main mural continued
Continued Mosaic tiling out side round pavement of the Lower Maluwa. Continued in toilets in ground & 1st floors of the Left wing building.
Plastering continued inside of the toilets in Left Wing building
The [...]

Read Full Post »

2009/05/23

The Mural on left side wall of the main mural continued
Continued final touches of Rough Tiling. Continued Mosaic tiling out side round pavement of the Lower Maluwa. Tiling continued in toilets in ground & 1st floors of the Left wing building.
Continued cutting & polishing of Marble.
The wooden block of Walakulu Bemma continued
Continued fixing fence [...]

Read Full Post »

2009/05/22

Started the mural on left side wall of the Main Mural
Continued final touches of Rough Tiling. Started Mosaic Tiling out side round pavement of the Lower Maluwa
Continued cutting & polishing of Marble.
The wooden block of Walakulu Bemma continued
Continued fixing fence posts on western boundary wall.
The new engineer arrived to premises in the evening.

Read Full Post »

2009/05/21

Painting of the mural completed
Completed grinding & polishing Stainless Steel Hand Rail.
Continued final touches of Rough Tiling.
Continued cutting & polishing of Marble.
The wooden block of Walakulu Bemma continued
Started fixing fence posts on western boundary wall.

Read Full Post »