2009/04/23
Apr 25th, 2009 by Kawshala Kapila
- Stainless Steel Hand Rail continued
- Continued laying of 6 in. concrete layer on eastern boundary wall
- Second coat terracotta paint on right wing roof continued replacing damaged tiles. Started two small pavilions
- Putting of damage areas of pillars inside of Siddhartha pavilion continued
- Glaze tile work continued in 1st floor in side of the left wing building
- Wiring inside of the left wing building continued
- Plumbing in side of the Left Wing Building continued
A Progress Review Meeting was held with the Contractor and discussed about Supplying of 30kVA Generator and Air Conditioners. Catalogs & Quotations were requested to approve. Contractor said the chain link can not be find here but, we still requested him to search from India. Requested to hire a Motor Grader & a Water Bowzer for the construction of the access road. Agreed to bring a carpenter to make the Decorative Valance Board. The Contractor was asked to improve the progress of Boundary Walls.