2009/04/23

  • Stainless Steel Hand Rail continued
  • Continued laying of 6 in. concrete layer on eastern boundary wall
  • Second coat terracotta paint on right wing roof continued replacing damaged tiles. Started two small pavilions
  • Putting of damage areas of pillars inside of Siddhartha pavilion continued
  • Glaze tile work continued in 1st floor in side of the left wing building
  • Wiring inside of the left wing building continued
  • Plumbing in side of the Left Wing Building continued

A Progress Review Meeting was held with the Contractor and discussed about Supplying of 30kVA Generator and Air Conditioners. Catalogs & Quotations were requested to approve. Contractor said the chain link can not be find here but, we still requested him to search from India. Requested to hire a Motor Grader & a Water Bowzer for the construction of the access road. Agreed to bring a carpenter to make the Decorative Valance Board. The Contractor was asked to improve the progress of Boundary Walls.