Apr 27th, 2009 by Kawshala Kapila
- Started repairing the damaged louvers of the left wing building
- Stainless Steel Hand Rail continued
- Started shuttering & reinforcement works on western boundary wall towards the main entrance
- Second coat terracotta paint on right wing roof continued replacing damaged tiles. Continued two small pavilions
- Putting of damage areas of pillars inside of Siddhartha pavilion completed
- Glaze tile work continued in 1st floor in side of the left wing building. Started ground floor
- Wiring inside of the left wing building continued
- Plumbing in side of the Left Wing Building continued
- Instructions were given to the technician regarding the Telephone & Computer networks