2009/04/24

  • Started repairing the damaged louvers of the left wing building
  • Stainless Steel Hand Rail continued
  • Started shuttering & reinforcement works on western boundary wall towards the main entrance
  • Second coat terracotta paint on right wing roof continued replacing damaged tiles. Continued two small pavilions
  • Putting of damage areas of pillars inside of Siddhartha pavilion completed
  • Glaze tile work continued in 1st floor in side of the left wing building. Started ground floor
  • Wiring inside of the left wing building continued
  • Plumbing in side of the Left Wing Building continued
  • Instructions were given to the technician regarding the Telephone & Computer networks