2009/04/26

  • Started Brick Wall on North Boundary wall for the Walakulu Bemma
  • Started laying of tiles inside of the Pound
  • Continued repairing the damaged louvers of the left wing building
  • Stainless Steel Hand Rail continued
  • Started concreting on western boundary wall towards the main entrance
  • Second coat terracotta paint on right wing roof continued replacing damaged tiles. completed two small pavilions
  • Glaze tile work continued in 1st floor in side of the left wing building. Continued ground floor
  • Wiring inside of the left wing building continued. Instructions were given to fix lights in small pavilions & garden around Bodhi Ghara with spot lights to Buddha Statue
  • Plumbing in side of the Left Wing Building continued