2009/04/27
Apr 30th, 2009 by Kawshala Kapila
- Continued Brick Wall on North Boundary wall for the Walakulu Bemma
- Continued laying of tiles inside of the Pound
- Continued repairing the damaged louvers of the left wing building
- Stainless Steel Hand Rail continued. 70% done.
- Completed concreting on western boundary wall towards the main entrance
- Second coat terracotta paint on right wing roof completed replacing damaged tiles. Small Pavilions Started.
- Glaze tile work continued in 1st floor in side of the left wing building. Continued ground floor. Steps started.
- Wiring inside of the left wing building continued.
- Plumbing in side of the Left Wing Building continued