2009/04/27

  • Continued Brick Wall on North Boundary wall for the Walakulu Bemma
  • Continued laying of tiles inside of the Pound
  • Continued repairing the damaged louvers of the left wing building
  • Stainless Steel Hand Rail continued. 70% done.
  • Completed concreting on western boundary wall towards the main entrance
  • Second coat terracotta paint on right wing roof completed replacing damaged tiles. Small Pavilions Started.
  • Glaze tile work continued in 1st floor in side of the left wing building. Continued ground floor. Steps started.
  • Wiring inside of the left wing building continued.
  • Plumbing in side of the Left Wing Building continued