2009/04/28

  • Continued Brick Wall on North Boundary wall for the Walakulu Bemma
  • Completed laying of tiles inside of the Pound
  • Continued repairing the damaged louvers of the left wing building
  • Stainless Steel Hand Rail continued.
  • Second coat terracotta paint on right wing roof completed replacing damaged tiles. Small Pavilions continued.
  • Glaze tile work continued in 1st floor in side of the left wing building. Continued ground floor. Steps continued.
  • Polishing of white Marble Started around Siddhartha Pavilion
  • 2 feet wide turfing started around the Second Maluwa
  • Started colour washing inside of the right wing building
  • Wiring inside of the left wing building continued.
  • Plumbing in side of the Left Wing Building continued
  • Invitations of the Ceremony given to local monasteries by Rev. Chandrarathana Thero
  • SFFL team arrived to Monastery safely