2009/05/23
May 31st, 2009 by Kawshala Kapila
- The Mural on left side wall of the main mural continued
- Continued final touches of Rough Tiling. Continued Mosaic tiling out side round pavement of the Lower Maluwa. Tiling continued in toilets in ground & 1st floors of the Left wing building.
- Continued cutting & polishing of Marble.
- The wooden block of Walakulu Bemma continued
- Continued fixing fence posts on western boundary wall.