2009/05/23

  • The Mural on left side wall of the main mural continued
  • Continued final touches of Rough Tiling. Continued Mosaic tiling out side round pavement of the Lower Maluwa. Tiling continued in toilets in ground & 1st floors of the Left wing building.
  • Continued cutting & polishing of Marble.
  • The wooden block of Walakulu Bemma continued
  • Continued fixing fence posts on western boundary wall.