2009/05/24

  • Continued fixing fence posts on western boundary wall.
  • Continued cutting & polishing of Marble.
  • The Mural on left side wall of the main mural continued
  • Continued Mosaic tiling out side round pavement of the Lower Maluwa. Continued in toilets in ground & 1st floors of the Left wing building.
  • Plastering continued inside of the toilets in Left Wing building
  • The wooden block of Walakulu Bemma continued