2009/05/26

  • Casting of Walakulu Bemma on the East Boundary wall along with the access road continued
  • Continued cutting & polishing of Marble.
  • Continued Mosaic tiling out side round pavement of the Lower Maluwa.
  • Continued floor tiling & wall tiling in toilets in ground & 1st floors of the Left wing building.
  • Plastering continued inside of the toilets in Left Wing building
  • The Mural on left side wall of the main mural continued
  • The wooden block of Walakulu Bemma completed
  • The alternator of the generator was replaced with new one with one year warranty.