2009/05/26
May 31st, 2009 by Kawshala Kapila
- Casting of Walakulu Bemma on the East Boundary wall along with the access road continued
- Continued cutting & polishing of Marble.
- Continued Mosaic tiling out side round pavement of the Lower Maluwa.
- Continued floor tiling & wall tiling in toilets in ground & 1st floors of the Left wing building.
- Plastering continued inside of the toilets in Left Wing building
- The Mural on left side wall of the main mural continued
- The wooden block of Walakulu Bemma completed
- The alternator of the generator was replaced with new one with one year warranty.