2009/06/19
Jun 19th, 2009 by Kawshala Kapila
- Casting of Walakulu Bemma on the North Boundary wall continued
- Brick form work of the base of the Pagoda started
- Bar bending work of the foundation, the columns & the Base of the Makara Thorana continued.
- Roof tile painting continued on the Right wing building
- Continued the door fixing in side of the Right wing building
- Continued cutting & polishing of Marble in Siddhartha Pavilion area.
- Tiling in side of the Right wing building continued. 90% completed
- Electrical wiring in side of the Right wing building continued