2009/06/20
Jun 23rd, 2009 by Kawshala Kapila
- Casting of Walakulu Bemma on the North Boundary wall continued with 05 moulds.
- Brick form work of the base of the Pagoda completed
- Bar bending work of the foundation, the columns & the Base of the Makara Thorana completed. Base Concreting was done
- Continued the door fixing in side of the Right wing building
- Continued cutting & polishing of Marble in Siddhartha Pavilion area.
- Tiling in side of the Right wing building continued. Work delayed due to the unavailability of tiles.