Jun 23rd, 2009 by Kawshala Kapila
- Casting of Walakulu Bemma on the North Boundary wall continued with 05 moulds.
- Bar bending work of the foundation of the Pagoda started
- Form work of the Beams of the Makara Thorana started
- Continued the door fixing in side of the Right wing building
- Continued cutting & polishing of Marble in Siddhartha Pavilion area.
- Tiling in side of the Right wing building continued. Work delayed due to the unavailability of tiles.