2009/06/22

  • Casting of Walakulu Bemma on the North Boundary wall continued with 05 moulds.
  • Bar bending work of the foundation of the Pagoda continued
  • Form work of the Beams of the Makara Thorana completed
  • Continued the door fixing in side of the Right wing building
  • Continued cutting & polishing of Marble in Siddhartha Pavilion area. Final touches of Steps started