2009/06/24
Jun 30th, 2009 by Kawshala Kapila
- Work delayed due to rain
- Beams of the Makara Thorana concreted
- Bar bending work of the foundation of the Pagoda continued
- Continued cutting & polishing of Marble. Final touches of Steps continued
- Partitioning of Bathrooms & toilets continued
- Continued repairing of Louvers of windows
- Plastering of Walakulu Bemma on the North Boundary wall continued
- Continued the door fixing in side of the Right wing building