2009/02/16

  • Cutting of foundations in Western & Southern boundary walls done.
  • Roof painting at Bodhi Ghara completed. Varnishing of timber underneath the Bodhi Ghara roof 60% completed.
  • Interior paint Colour selected
  • Cleaning of wire cut brick walls in Maluwa area 45% completed. Started the cleaning with Oxalic Acid.
  • Cutting and laying of Green Marble at the steps of Makara Thorana done. Night shift for this work going on
  • Deep well dug to a depth of 285 ft
  • Site clearing along flower beds completed
  • Chipping along the front landing completed.
  • Member Secretary of Lumbini Development Trust Visited the Site.
  • Overall progress improving