2009/02/16
Feb 18th, 2009 by Kawshala Kapila
- Cutting of foundations in Western & Southern boundary walls done.
- Roof painting at Bodhi Ghara completed. Varnishing of timber underneath the Bodhi Ghara roof 60% completed.
- Interior paint Colour selected
- Cleaning of wire cut brick walls in Maluwa area 45% completed. Started the cleaning with Oxalic Acid.
- Cutting and laying of Green Marble at the steps of Makara Thorana done. Night shift for this work going on
- Deep well dug to a depth of 285 ft
- Site clearing along flower beds completed
- Chipping along the front landing completed.
- Member Secretary of Lumbini Development Trust Visited the Site.
- Overall progress improving