2009/02/17
Feb 20th, 2009 by Kawshala Kapila
- Cutting & Placing Green Marble continued with a slow progress. Instructed to employ another team to catch-up delayed work.
- Underneath varnishing both Bodhi Ghara & 2 ½ of the small pavilions continued.
- Clearing of Flower beds done.
- Ground & 1st floors applied potty of Left wing building.
- Had a discussion with the Contractors and informed to speed up the work. They were explained about the delayed targets.
- In deep well, all the pipes sent down were taken out to remove the mud which has got stuck in pipes. Restarted digging.
- Cleaning of wire cut brick walls with Oxalic acid continued. 60% completed.
- Part of Materials such as metal, cement & sand were transported to site.
- Foundations of the boundary wall on the left side of the main entrance done to a height of 1 ½ feet.
- A simple design was given to a Contractor to make the hand rails.