2009/02/17

  • Cutting & Placing Green Marble continued with a slow progress. Instructed to employ another team to catch-up delayed work.
  • Underneath varnishing both Bodhi Ghara & 2 ½ of the small pavilions continued.
  • Clearing of Flower beds done.
  • Ground & 1st floors applied potty of Left wing building.
  • Had a discussion with the Contractors and informed to speed up the work. They were explained about the delayed targets.
  • In deep well, all the pipes sent down were taken out to remove the mud which has got stuck in pipes. Restarted digging.
  • Cleaning of wire cut brick walls with Oxalic acid continued. 60% completed.
  • Part of Materials such as metal, cement & sand were transported to site.
  • Foundations of the boundary wall on the left side of the main entrance done to a height of 1 ½ feet.
  • A simple design was given to a Contractor to make the hand rails.