2009/02/18
Feb 20th, 2009 by Kawshala Kapila
- Cutting & Placing Green Marble continued still not up to the target.
- Roof painting of 04 small pavilions completed. ½ of the southern pavilion done.
- Foundation of the right side of main entrance finished to a height of 1 ft. Left side completed.
- 03 tipper loads approximately 6-8 cubes of fertile earth for the flower beds were sent to the site by the courtesy of Lumbini Development Trust on our request.
- A Contractor came for the planting of flowers in our flower beds. He was refused because of the high rates.
- Had a discussion with the Contractors in the evening regarding the progress and again informed to speed up the work as the progress is low. Contractor requested for the balance mobilization advance.
- Showed the present progress of the site via internet to Mr. Anuradha Wickramasinghe and Contractor was given an opportunity to speak with him. Mr. Wickramasinghe advised us to pay him 0.6 M out of 1 M Cheque written in favour of the Contractor and to get the balance 0.4 M for the expenses.
- Ranweta & Pinnacles were given to a Contractor to cast from Katmandu.
- Deep well dug to a depth of 290 ft.