2009/02/19

  • Hon. Minister Dew Gunasekara & Hon. MP Lama Khenpo Chimed Tsering visited the site in the morning.
  • Painting of roof 06 small pavilions, Bodhi Ghara & 01 Large pavilion completed.
  • Roof cleaning done on 04 small pavilion roofs to apply terracotta paint.
  • Varnishing roof underneath Bodhi Ghara & 01 small pavilion completed.
  • Polishing of Ranweta with Braso completed.
  • Colour Painting of left wing building ground floor & 1st floor 50% completed.
  • Pillars of the Bodhi Ghara & the circular wall in the Bodhi Ghara applied the 1st coat of brilliant white paint
  • Green Marble on the main entrance steps & 2/3 of the landing completed. Walls of the left side Moat green marble completed. Started laying Red marble on the left side steps.
  • Wire cut brick cleaning 75% done.
  • Deep well dug to a depth of 300 ft.
  • Filling of the flower beds with soil sent by LDT 50% done and 01 tractor load of cow dung transported to the site.
  • More Materials such as Green Marble, Metal, Interlocking tiles, Sand, reinforcement & cement transported to the site.
  • Cutting of foundation in the eastern wall started 60% completed. RR Masonry work continued on the either sides of main entrance.
  • Under the steps on both sides and in Siddhartha pavilion were cleaned to lay concrete.
  • Overall progress improving