2009/02/21
Feb 21st, 2009 by Kawshala Kapila
- Finally received water still mud clearing is done. Steady flow expected tomorrow.
- Marble work 1388 sqft done. Red 360 sqft completed.
- Rough tile work 570 sqft completed. 9000 tiles brought to the site.
- Terracotta painting on roofs almost 10 small pavilions and 01 large pavilion completed.
- Varnishing underneath roof Bodhi Ghara & 03 small pavilions done. 4800 sqft approximately
- Wire cut brick wall immediate after Bodhi Ghara first coat done. 1400 sqft completed.
- White emulsion painting in Bodhi Ghara & Pillars completed. 2100 sqft.
- Colour painting in ground & 1st floor 75% done.
- Joint measurements were taken with the Contractor for the 1st Part payment which will be forwarded tomorrow.
- Foundation cutting in the second block eastern side continued. Foundation laying with RR Masonry continued in total southern walls.
- Clearing of Siddhartha pavilion done.
- Filling of the flower beds with soil sent by LDT 90% done.
- Another part of the materials such as Rubble, Sand & Rough tiles received.
- Instructions were given to the Contractor to employ another labour gang to speed up Marble laying & Tiling.
- Overall progress improving