2009/02/21

  • Finally received water still mud clearing is done. Steady flow expected tomorrow.
  • Marble work 1388 sqft done. Red 360 sqft completed.
  • Rough tile work 570 sqft completed. 9000 tiles brought to the site.
  • Terracotta painting on roofs almost 10 small pavilions and 01 large pavilion completed.
  • Varnishing underneath roof Bodhi Ghara & 03 small pavilions done. 4800 sqft approximately
  • Wire cut brick wall immediate after Bodhi Ghara first coat done. 1400 sqft completed.
  • White emulsion painting in Bodhi Ghara & Pillars completed. 2100 sqft.
  • Colour painting in ground & 1st floor 75% done.
  • Joint measurements were taken with the Contractor for the 1st Part payment which will be forwarded tomorrow.
  • Foundation cutting in the second block eastern side continued. Foundation laying with RR Masonry continued in total southern walls.
  • Clearing of Siddhartha pavilion done.
  • Filling of the flower beds with soil sent by LDT 90% done.
  • Another part of the materials such as Rubble, Sand & Rough tiles received.
  • Instructions were given to the Contractor to employ another labour gang to speed up Marble laying & Tiling.
  • Overall progress improving