2009/02/22
Feb 23rd, 2009 by Kawshala Kapila
- Deep well cleared but no free flow. Water quality is good.
- Marble work up to the 4th landing of the steps was done. Green marble shortage at site. The Contractor promised to bring tomorrow.
- Terracotta first coat finished except the large two buildings and the Siddhartha pavilion.
- Varnishing 04 small pavilions finished. Started under the Siddhartha pavilion but had to stop due to shortage of varnish. A hive full of wasp attacked few painters who were not serious.
- White emulsion ceiling and the pillars of the left wing finished. Colour painting finished up to 2 feet above the floor level which will be done after tile work.
- Foundation laying of Southern & Eastern walls continued.
- Cleaning wire cut bricks continued around the premises.
- Had a progress review meeting with the Contractor.