2009/02/23

  • Public Holiday (Maha Shivrathri Day). Hence, many labourers did not turn up.
  • Trimming flower trees in the compound started.
  • Painting second coat emulsion continued in Siddhartha pavilion
  • Varnishing underneath of Siddhartha pavilion started
  • Roof cleaning of right wing building started.
  • Rough tiling one small pavilion done. Moat (left wall) started.
  • Wire cut brick cleaning continued.
  • Only one team worked in marble laying. Progress is slow.
  • Generator packed up. No night shift.