2009/02/23
Feb 26th, 2009 by Kawshala Kapila
- Public Holiday (Maha Shivrathri Day). Hence, many labourers did not turn up.
- Trimming flower trees in the compound started.
- Painting second coat emulsion continued in Siddhartha pavilion
- Varnishing underneath of Siddhartha pavilion started
- Roof cleaning of right wing building started.
- Rough tiling one small pavilion done. Moat (left wall) started.
- Wire cut brick cleaning continued.
- Only one team worked in marble laying. Progress is slow.
- Generator packed up. No night shift.