2009/02/24
Feb 26th, 2009 by Kawshala Kapila
- Work delayed due to electricity & generator failure
- Red Marble laying at the landing of the steps in progress.
- Rough tiles left wing moat one wall completed.
- Terracotta second coat started in Siddhartha pavilion
- Varnishing underneath of Siddhartha pavilion (second coat), 02 small pavilions (first coat) done.
- Concreting under left steps done.
- Green marble brought to site at 4 pm.
- Laying of Interlocking tiles started.
- Joint measurements were done for the 1st Part payment to the Contractor.
- Foundation cutting in North boundary wall is in progress.
- Sri Lankan team arrived at 11.00 p