2009/02/24

  • Work delayed due to electricity & generator failure
  • Red Marble laying at the landing of the steps in progress.
  • Rough tiles left wing moat one wall completed.
  • Terracotta second coat started in Siddhartha pavilion
  • Varnishing underneath of Siddhartha pavilion (second coat), 02 small pavilions (first coat) done.
  • Concreting under left steps done.
  • Green marble brought to site at 4 pm.
  • Laying of Interlocking tiles started.
  • Joint measurements were done for the 1st Part payment to the Contractor.
  • Foundation cutting in North boundary wall is in progress.
  • Sri Lankan team arrived at 11.00 p