2009/02/25

  • Trimming flower beds continued.
  • Roof clearing & applying terracotta of the right wing building started.
  • Laying of Interlocking tiles continued on both sides
  • Sri Lankan team started the Garden Beautification
  • Rough tile work on left wing moat completed.
  • Red Marble laying at the landing of the steps continued.
  • Concreting under the left main steps & steps of lower maluwa done.
  • Part of pebbles, cement & steel brought to site.
  • Windows of left wing sand papering in preparation for the final coat