2009/02/25
Feb 26th, 2009 by Kawshala Kapila
- Trimming flower beds continued.
- Roof clearing & applying terracotta of the right wing building started.
- Laying of Interlocking tiles continued on both sides
- Sri Lankan team started the Garden Beautification
- Rough tile work on left wing moat completed.
- Red Marble laying at the landing of the steps continued.
- Concreting under the left main steps & steps of lower maluwa done.
- Part of pebbles, cement & steel brought to site.
- Windows of left wing sand papering in preparation for the final coat