Feed on
Posts
Comments

2009/03/20

  • Continued foundations of the boundary walls North side
  • Varnishing underneath Bodhi Ghara completed
  • First coat varnishing started out side of walls of the Left wing Building
  • Thunder showers at mid night lasted for almost one hour