2009/03/23
Mar 24th, 2009 by Kawshala Kapila
- Foundations of the boundary walls North side completed
- White Marble work inside of the Siddhartha pavilion continued. 50% completed
- Roof timber varnishing right wing building 1st coat started. 40% completed.
- Part of Materials such as Rubble, Glaze Tiles and Sand transported to the site