Mar 24th, 2009 by Kawshala Kapila
- Started the next step of North boundary walls
- White Marble work inside of the Siddhartha pavilion continued. 90% completed
- Laying of Green Marble in the Small pavilion, front of Left wing building started.
- Roof timber varnishing right wing building 1st coat continued. 60% completed.
- Another gang of skilled labourers came to site for Tile work