2009/03/24

  • Started the next step of North boundary walls
  • White Marble work inside of the Siddhartha pavilion continued. 90% completed
  • Laying of Green Marble in the Small pavilion, front of Left wing building started.
  • Roof timber varnishing right wing building 1st coat continued. 60% completed.
  • Another gang of skilled labourers came to site for Tile work