2009/03/25

  • Proceeded to Dhangadi (10 Hour journey,  One way) to select the Boys to be ordained.
  • Obtained over the phone the following work progress during the day.
  • Continued the next step of North boundary walls.
  • White Marble work inside of the Siddhartha pavilion completed.
  • Laying of Green Marble in the Small pavilion, front of Left wing building continued. 50% completed.
  • Glaze Tiling on cement benches in side of the Right wing building Started. The second floor of the Left wing building started