2009/03/26
Mar 27th, 2009 by Kawshala Kapila
- Interview was held at Dhangadi Buddhist Temple. 11 boys were Selected. The responsible Lady also in one of the pictures.
- Continued the next step of North boundary walls. 50% completed
- Laying of Green Marble in the Small pavilion, front of Left wing building completed.
- Glaze Tiling on cement benches in side of the Right wing building continued except one bench.
- The hall of the second floor of the Left wing building continued. 50% completed