2009/03/27
Mar 27th, 2009 by Kawshala Kapila
- Completed the North boundary walls to 18 x 18 in. Eastern Side finished up to 60%
- Glaze Tiling on cement benches in side of the Right wing building completed.
- The hall of the second floor of the Left wing building continued. 90% completed. Balcony 30% done.
- Varnishing underneath right wing building 90% completed
- Again the Strike started and Police have enforced curfew at Bhairahawa & Butwal Areas