2009/03/27

  • Completed the North boundary walls to 18 x 18 in. Eastern Side finished up to 60%
  • Glaze Tiling on cement benches in side of the Right wing building completed.
  • The hall of the second floor of the Left wing building continued. 90% completed. Balcony 30% done.
  • Varnishing underneath right wing building 90% completed
  • Again the Strike started and Police have enforced curfew at Bhairahawa & Butwal Areas