2009/03/29

  • Till 12 noon the Strike and the curfew lifted. No material can be transported.
  • Completed the North boundary walls to 18 in x 18 in as shown in figure.
  • Glaze tiling could not be done because of the unavailability of tile transportation.
  • Rough tiling on Outer Curved Mote walls 90% completed. Southern Large pavilion 90% completed.
  • Varnishing underneath right wing building 2nd coat continued.