2009/04/20

  • Completed laying of White Marble under stair
  • Rough tile work on Round walkways to the Uda Maluwa & steps completed. Finishing touches to be started later
  • Stainless Steel Hand Rail continued
  • The corners of the Western & Southern boundary walls on the concrete beams continued.
  • Second coat terracotta paint on right wing roof started replacing damaged tiles
  • Glaze tile work started in 1st floor in side of the left wing building
  • Wiring inside of the left wing building continued
  • Plumbing in side of the Left Wing Building continued