2009/04/20
Apr 25th, 2009 by Kawshala Kapila
- Completed laying of White Marble under stair
- Rough tile work on Round walkways to the Uda Maluwa & steps completed. Finishing touches to be started later
- Stainless Steel Hand Rail continued
- The corners of the Western & Southern boundary walls on the concrete beams continued.
- Second coat terracotta paint on right wing roof started replacing damaged tiles
- Glaze tile work started in 1st floor in side of the left wing building
- Wiring inside of the left wing building continued
- Plumbing in side of the Left Wing Building continued