Apr 25th, 2009 by Kawshala Kapila
- Stainless Steel Hand Rail continued
- Started laying of 6 in. concrete layer on eastern boundary wall
- The corners of the Western & Southern boundary walls on the concrete beams completed.
- Second coat terracotta paint on right wing roof continued replacing damaged tiles
- Glaze tile work continued in 1st floor in side of the left wing building
- Wiring inside of the left wing building continued
- Plumbing in side of the Left Wing Building continued