2009/04/21

  • Stainless Steel Hand Rail continued
  • Started laying of 6 in. concrete layer on eastern boundary wall
  • The corners of the Western & Southern boundary walls on the concrete beams completed.
  • Second coat terracotta paint on right wing roof continued replacing damaged tiles
  • Glaze tile work continued in 1st floor in side of the left wing building
  • Wiring inside of the left wing building continued
  • Plumbing in side of the Left Wing Building continued