2009/04/22
Apr 25th, 2009 by Kawshala Kapila
- Stainless Steel Hand Rail continued
- Continued laying of 6 in. concrete layer on eastern boundary wall
- Second coat terracotta paint on right wing roof continued replacing damaged tiles
- Putting of damage areas of pillars inside of Siddhartha pavilion started
- Glaze tile work continued in 1st floor in side of the left wing building
- Wiring inside of the left wing building continued
- Plumbing in side of the Left Wing Building continued