Jun 30th, 2009 by Kawshala Kapila
- Casting of Walakulu Bemma on the South Boundary wall started. North Walakulu Bemma plastering continued
- Continued cutting & polishing of Marble. Final touches of Steps continued
- The Form Work of Pillars of the Makara Thorana started
- Continued repairing of Louvers of windows
Posted in Progress | No Comments »
Jun 30th, 2009 by Kawshala Kapila
- Pagoda Base concreted
- Continued cutting & polishing of Marble. Final touches of Steps continued
- Partitioning of Bathrooms & toilets continued
- Continued repairing of Louvers of windows
- Plastering of Walakulu Bemma on the North Boundary wall continued
Posted in Progress | No Comments »
Jun 30th, 2009 by Kawshala Kapila
- Work delayed due to rain
- Beams of the Makara Thorana concreted
- Bar bending work of the foundation of the Pagoda continued
- Continued cutting & polishing of Marble. Final touches of Steps continued
- Partitioning of Bathrooms & toilets continued
- Continued repairing of Louvers of windows
- Plastering of Walakulu Bemma on the North Boundary wall continued
- Continued the door fixing in side of the Right wing building
Posted in Progress | No Comments »
Jun 24th, 2009 by Kawshala Kapila
- Casting of Walakulu Bemma on the North Boundary wall continued with 05 moulds.
- Bar bending work of the foundation of the Pagoda continued
- Form work of the Beams of the Makara Thorana completed
- Continued the door fixing in side of the Right wing building
- Continued cutting & polishing of Marble in Siddhartha Pavilion area. Final touches of Steps continued
Posted in Progress | No Comments »
Jun 23rd, 2009 by Kawshala Kapila
- Casting of Walakulu Bemma on the North Boundary wall continued with 05 moulds.
- Bar bending work of the foundation of the Pagoda continued
- Form work of the Beams of the Makara Thorana completed
- Continued the door fixing in side of the Right wing building
- Continued cutting & polishing of Marble in Siddhartha Pavilion area. Final touches of Steps started
Posted in Progress | No Comments »
Jun 23rd, 2009 by Kawshala Kapila
- Casting of Walakulu Bemma on the North Boundary wall continued with 05 moulds.
- Bar bending work of the foundation of the Pagoda started
- Form work of the Beams of the Makara Thorana started
- Continued the door fixing in side of the Right wing building
- Continued cutting & polishing of Marble in Siddhartha Pavilion area.
- Tiling in side of the Right wing building continued. Work delayed due to the unavailability of tiles.
Posted in Progress | No Comments »
Jun 23rd, 2009 by Kawshala Kapila
- Casting of Walakulu Bemma on the North Boundary wall continued with 05 moulds.
- Brick form work of the base of the Pagoda completed
- Bar bending work of the foundation, the columns & the Base of the Makara Thorana completed. Base Concreting was done
- Continued the door fixing in side of the Right wing building
- Continued cutting & polishing of Marble in Siddhartha Pavilion area.
- Tiling in side of the Right wing building continued. Work delayed due to the unavailability of tiles.
Posted in Progress | No Comments »
Jun 19th, 2009 by Kawshala Kapila
- Casting of Walakulu Bemma on the North Boundary wall continued
- Brick form work of the base of the Pagoda started
- Bar bending work of the foundation, the columns & the Base of the Makara Thorana continued.
- Roof tile painting continued on the Right wing building
- Continued the door fixing in side of the Right wing building
- Continued cutting & polishing of Marble in Siddhartha Pavilion area.
- Tiling in side of the Right wing building continued. 90% completed
- Electrical wiring in side of the Right wing building continued
Posted in Progress | No Comments »
Jun 19th, 2009 by Kawshala Kapila
- Casting of Walakulu Bemma on the North Boundary wall continued
- Screed concreted the foundation of the Pagoda
- Bar bending work of the foundation, the columns & the Base of the Makara Thorana continued.
- Roof tile painting continued on the Right wing building
- Continued the door fixing in side of the Right wing building
- Continued cutting & polishing of Marble.
- Tiling in side of the Right wing building continued. 90% completed
Posted in Progress | No Comments »
Jun 19th, 2009 by Kawshala Kapila
- Casting of Walakulu Bemma on the North Boundary wall continued
- Cutting of foundation of the Pagoda was completed
- Bar bending work of the foundation of the Makara Thorana continued
- Roof tile painting continued on the Right wing building
- Continued the door fixing in side of the Right wing building
- Continued cutting & polishing of Marble.
Posted in Progress | No Comments »