2009/06/26

  • Casting of Walakulu Bemma on the South Boundary wall started. North Walakulu Bemma plastering continued
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • The Form Work of Pillars of the Makara Thorana started
  • Continued repairing of Louvers of windows

2009/06/25

  • Pagoda Base concreted
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • Partitioning of Bathrooms & toilets continued
  • Continued repairing of Louvers of windows
  • Plastering of Walakulu Bemma on the North Boundary wall continued

2009/06/24

  • Work delayed due to rain
  • Beams of the Makara Thorana concreted
  • Bar bending work of the foundation of the Pagoda continued
  • Continued cutting & polishing of Marble. Final touches of Steps continued
  • Partitioning of Bathrooms & toilets continued
  • Continued repairing of Louvers of windows
  • Plastering of Walakulu Bemma on the North Boundary wall continued
  • Continued the door fixing in side of the Right wing building

2009/06/23

  • Casting of Walakulu Bemma on the North Boundary wall continued with 05 moulds.
  • Bar bending work of the foundation of the Pagoda continued
  • Form work of the Beams of the Makara Thorana completed
  • Continued the door fixing in side of the Right wing building
  • Continued cutting & polishing of Marble in Siddhartha Pavilion area. Final touches of Steps continued

2009/06/22

  • Casting of Walakulu Bemma on the North Boundary wall continued with 05 moulds.
  • Bar bending work of the foundation of the Pagoda continued
  • Form work of the Beams of the Makara Thorana completed
  • Continued the door fixing in side of the Right wing building
  • Continued cutting & polishing of Marble in Siddhartha Pavilion area. Final touches of Steps started

2009/06/21

  • Casting of Walakulu Bemma on the North Boundary wall continued with 05 moulds.
  • Bar bending work of the foundation of the Pagoda started
  • Form work of the Beams of the Makara Thorana started
  • Continued the door fixing in side of the Right wing building
  • Continued cutting & polishing of Marble in Siddhartha Pavilion area.
  • Tiling in side of the Right wing building continued. Work delayed due to the unavailability of tiles.

2009/06/20

  • Casting of Walakulu Bemma on the North Boundary wall continued with 05 moulds.
  • Brick form work of the base of the Pagoda completed
  • Bar bending work of the foundation, the columns & the Base of the Makara Thorana completed. Base Concreting was done
  • Continued the door fixing in side of the Right wing building
  • Continued cutting & polishing of Marble in Siddhartha Pavilion area.
  • Tiling in side of the Right wing building continued. Work delayed due to the unavailability of tiles.

2009/06/19

  • Casting of Walakulu Bemma on the North Boundary wall continued
  • Brick form work of the base of the Pagoda started
  • Bar bending work of the foundation, the columns & the Base of the Makara Thorana continued.
  • Roof tile painting continued on the Right wing building
  • Continued the door fixing in side of the Right wing building
  • Continued cutting & polishing of Marble in Siddhartha Pavilion area.
  • Tiling in side of the Right wing building continued. 90% completed
  • Electrical wiring in side of the Right wing building continued

2009/06/18

  • Casting of Walakulu Bemma on the North Boundary wall continued
  • Screed concreted the foundation of the Pagoda
  • Bar bending work of the foundation, the columns & the Base of the Makara Thorana continued.
  • Roof tile painting continued on the Right wing building
  • Continued the door fixing in side of the Right wing building
  • Continued cutting & polishing of Marble.
  • Tiling in side of the Right wing building continued. 90% completed

2009/06/17

  • Casting of Walakulu Bemma on the North Boundary wall continued
  • Cutting of foundation of the Pagoda was completed
  • Bar bending work of the foundation of the Makara Thorana continued
  • Roof tile painting continued on the Right wing building
  • Continued the door fixing in side of the Right wing building
  • Continued cutting & polishing of Marble.