2009/06/16

  • Casting of Walakulu Bemma on the North Boundary wall continued
  • Cutting of foundation of the Pagoda was continued
  • Steel work & bar bending work of the foundation of the Makara Thorana continued
  • Roof tile painting continued on the Right wing building
  • Continued the door fixing in side of the Right wing building
  • Continued cutting & polishing of Marble.
  • The Artistic Paintings underneath the slab completed.

2009/06/15

  • Casting of Walakulu Bemma on the North Boundary wall continued
  • Cutting of foundation of the Pagoda was continued
  • Steel work of the foundation of the Makara Thorana continued
  • Roof tile painting continued on the Right wing building
  • Foundation of the Makara Thorana Leveled and screed concreting done
  • Continued the door fixing in side of the Right wing building
  • Continued cutting & polishing of Marble.
  • The Artistic Paintings underneath the slab continued.

2009/06/14

  • Casting of Walakulu Bemma on the North Boundary wall continued
  • Cutting of foundation of the Pagoda was started with the chanting of Seth Pirith by the Ven. Dr. Rambukwelle Chandrarathana Thero with the 07 Little Monks
  • Foundation of the Makara Thorana excavated and completed
  • Steel work of the foundation of the Makara Thorana continued
  • Roof tile painting continued on the Right wing building
  • Continued the door fixing in side of the Right wing building
  • Continued cutting & polishing of Marble.
  • The Artistic Paintings underneath the slab continued.

2009/06/13

  • Casting of Walakulu Bemma on the North Boundary wall started
  • Clearing continued in the construction area of the Pagoda
  • Steel work of the foundation of the Makara Thorana continued
  • Roof tile painting started on the Right wing building
  • Started the door fixing in side of the Right wing building
  • Continued cutting & polishing of Marble.
  • The Artistic Paintings underneath the slab continued. Mr. Jayasiri Semage Left to Sri Lanka

2009/06/12

  • Casting of Walakulu Bemma on the East Boundary wall completed
  • Clearing continued in the construction area of the Pagoda
  • Steel work of the foundation of the Makara Thorana continued
  • Continued cutting & polishing of Marble.
  • The Artistic Paintings underneath the slab continued.

2009/06/11

  • Work Stopped due to the unavailability of workers because of the strike
  • Casting of Walakulu Bemma on the East Boundary wall Continued with 05 Moulds
  • The construction area of the Pagoda was cleared
  • Steel work of the foundation of the Makara Thorana continued
  • Continued cutting & polishing of Marble.
  • The Artistic Paintings underneath the slab continued.

2009/06/10

  • Sri Lankan working committee left Lumbini in the morning.
  • Casting of Walakulu Bemma on the East Boundary wall Continued with 05 Moulds
  • Steel work of the foundation of the Makara Thorana started
  • Continued cutting & polishing of Marble.
  • The Artistic Paintings underneath the slab continued.

2009/06/09

  • Sri Lankan working committee visited the site. The Foundation detail of the Pagoda which is going to be constructed was given.
  • Casting of Walakulu Bemma on the East Boundary wall Continued with 05 Moulds.
  • Cutting of the foundation of the Makara Thorana continued
  • Continued cutting & polishing of Marble.
  • Completed floor tiling & wall tiling in toilets in side of the Left wing building.
  • The Artistic Paintings underneath the slab continued.

2009/06/08

  • Casting of Walakulu Bemma on the East Boundary wall Continued with 05 Molds.
  • Cutting of the foundation of the Makara Thorana continued
  • Continued cutting & polishing of Marble.
  • Completed floor tiling & wall tiling in toilets in side of the Left wing building.
  • The Artistic Paintings underneath the slab started.

2009/06/07

  • Casting of Walakulu Bemma on the East Boundary wall Continued with 05 Molds.
  • Cutting of the foundation of the Makara Thorana continued
  • Brick work of the Front boundary wall completed.
  • Continued cutting & polishing of Marble.
  • Mosaic tiling out side round pavement of the Lower Maluwa completed
  • Continued floor tiling & wall tiling in toilets in side of the Left wing building.
  • The Mural on Right side wall of the main mural completed.